Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15 | 15 | 2.000 | 13 | 13.000 | 13.000 |
70W454 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली संख्या-48456, दिनांक 10.08.2023
TS Amount (lakhs) : 340.19 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
340.19
Resanction Cost :
340.19
Tentative Cost :
340.19
Exp. Upto Last Fy : 77.25
For CFY 2024-2025
Remaining : 262.94
Demand : 262.94
Allotment : 100.00
Exp in CFY : 87.02
Total Up to Date Exp : 164.26
Work completed
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 100 %
Sanction on :
11 months 1 week ago
10 Aug 2023
Tentative Completion date:
2 days 5 hours ago
15 Jul 2024
Actual Completion Date:
1 month 2 days ago
15 Jun 2024
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्वों का अन्तिमीकरण किया जा रहा है। -- as on 13-Jun-2024
Physical Peramenters