Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 15 | 15 | 2.000 | 13 | 13.000 | 0.000 |
70W454 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली संख्या-48456, दिनांक 10.08.2023
TS Amount (lakhs) : 340.19 Lacs
Financial Detail
Sanction Cost : 340.19 Lacs
Resanction Cost : 340.19 Lacs
Exp. Upto Last Fy : 77.25 Lacs
For CFY 2024-2025
Remaining : 262.94 Lacs
Demand : 262.94 Lacs
Allotment : 100.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 77.25 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 40 %
Sanction on :
9 months 1 week ago
10 Aug 2023
Tentative Completion date:
2 weeks 2 days from now
05 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
PC का कार्य प्रगति पर। -- as on 28-Mar-2024