Work Profile Report [70W465]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : जिलाधिकारी पौड़ी के पत्रांक 603/13-मु0रा0ले0 (दै0आ0)/2023-24, पौड़ी, दि0 24.08.2023
TS Amount (lakhs) : 14.83 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
14.83
Resanction Cost :
14.83
Tentative Cost :
14.83
Exp. Upto Last Fy :
10.72
For CFY 2024-2025
Remaining :
4.11
Demand :
3.71
Allotment :
0.40
Exp in CFY :
0.00
Total Up to Date Exp :
10.72
Work completed
Sanction on : 1 year 2 months ago
24 Aug 2023
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 7 months 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का अन्तिमीकरण किया जा रहा है। -- as on 30-Jan-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand