Work Profile Report [70W467]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन की ई0-पत्रावली सं0 26505, दि0 08.09.2023
TS Amount (lakhs) : 59.88 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
59.88
Resanction Cost :
59.88
Tentative Cost :
59.88
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
59.88
Demand :
25.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
0.00
Construction Started
Sanction on : 1 year 2 months ago
08 Sep 2023
Physical Progress:
At start of FY 2024-2025 :
2 %
Up to Date :
2 %
Tentative Completion date on : 3 months 4 days from now
28 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
अनुबन्ध गठित। कार्य प्रारम्भ किया जा रहा है। -- as on 09-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand