Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.85 | 1.85 | 0.000 | 1.85 | 1.000 | 0.000 |
70W467 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0-पत्रावली सं0 26505, दि0 08.09.2023
TS Amount (lakhs) : 59.88 Lacs
Financial Detail
Sanction Cost : 59.88 Lacs
Resanction Cost : 59.88 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 59.88 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 2 %
Up to Date : 2 %
Sanction on :
8 months 1 week ago
08 Sep 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित। कार्य प्रगति पर। -- as on 28-Mar-2024
Physical Peramenters