Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.750 | 2.25 | 2.250 | 0.000 |
70W468 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0-पत्रावली सं0 26505, दि0 08.09.2023
TS Amount (lakhs) : 97.06 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
97.06
Resanction Cost :
97.06
Tentative Cost :
97.06
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 96.96
Demand : 44.84
Allotment : 0.00
Exp in CFY : 14.84
Total Up to Date Exp : 14.93
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 60 %
Sanction on :
10 months 1 week ago
08 Sep 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य प्रगति पर। -- as on 28-Mar-2024
Physical Peramenters