Administrative Approval Detail : शासन की ई0 पत्रावली सं0 35543, दि0 06.11.2023
TS Amount (lakhs) : 394.81 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
394.81
Resanction Cost :
394.81
Tentative Cost :
394.81
Exp. Upto Last Fy :
85.55
For CFY 2024-2025
Remaining :
309.26
Demand :
282.44
Allotment :
250.00
Exp in CFY :
174.48
Total Up to Date Exp :
260.04
Construction Started
Sanction on : 1 year 1 month ago
06 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
20 %
Up to Date :
95 %
Tentative Completion date on : 2 months 23 hours from now
26 Feb 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
पी0सी0 का कार्य पूर्ण। अवशेष कार्य प्रगति पर। -- as on 30-Nov-2024