Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 5.000 | 0.000 |
70W479 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 35543, दि0 06.11.2023
TS Amount (lakhs) : 394.81 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
394.81
Resanction Cost :
394.81
Tentative Cost :
394.81
Exp. Upto Last Fy : 85.55
For CFY 2024-2025
Remaining : 309.26
Demand : 125.00
Allotment : 110.00
Exp in CFY : 74.65
Total Up to Date Exp : 160.20
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 45 %
Sanction on :
8 months 1 week ago
06 Nov 2023
Tentative Completion date:
7 months 1 week from now
26 Feb 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
इण्टर कोट का कार्य पूर्ण। टोप कोट का कार्य प्रगति पर। -- as on 22-May-2024
Physical Peramenters