Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.500 | 0.5 | 0.000 | 0.000 |
70W48 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : fजलाfधकारी,पौड़ी के पत्रांक 487/fज0यो0/ लो0fन0fव0/2015-16 fद0 08.07.2015
TS Amount (lakhs) : 46.62 Lacs
Financial Detail
Sanction Cost : 46.62 Lacs
Resanction Cost : 46.62 Lacs
Exp. Upto Last Fy : 19.93 Lacs
For CFY 2024-2025
Remaining : 26.69 Lacs
Demand : 20.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 19.93 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 70 %
Up to Date : 70 %
Sanction on :
8 years 10 months ago
08 Jul 2015
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सैद्वान्तिक स्वीकृति प्राप्त रू0 1651854.00 मात्र का एन0पी0वी0 एवं वृक्षों के रख-रखाव हेतु धनराशि व विभाग में जमा की जानी है। जिस हेतु प्रमुख अभियन्ता लो0नि0वि0 देहरादून से अतिरिक्त धनराशि की मांग की जा रही है। पहाड़ कटान का कार्य पूर्ण। दायित्व अवशेष। पार्ट-2 के कार्य प्रगति पर। -- as on 28-Mar-2024
Physical Peramenters