Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 3.000 | 0.000 |
70W482 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 50713, दिनांक 19.12.2023।
TS Amount (lakhs) : 200.68 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
200.68
Resanction Cost :
200.68
Tentative Cost :
200.68
Exp. Upto Last Fy : 0.30
For CFY 2024-2025
Remaining : 200.38
Demand : 45.00
Allotment : 10.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.30
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 20 %
Sanction on :
6 months 4 weeks ago
19 Dec 2023
Tentative Completion date:
7 months 3 weeks from now
14 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार निर्माण का कार्य पूर्ण। स्कपर एंव सोलिंग का कार्य प्रगति पर। -- as on 25-Jun-2024