Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 2.000 | 0.000 |
70W499 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 38666, दि0 10.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
116.93
Resanction Cost :
116.93
Tentative Cost :
116.93
Exp. Upto Last Fy : 0.22
For CFY 2024-2025
Remaining : 116.71
Demand : 97.39
Allotment : 50.00
Exp in CFY : 47.39
Total Up to Date Exp : 47.61
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 20 %
Sanction on :
6 months 1 week ago
10 Jan 2024
Tentative Completion date:
1 month 2 weeks from now
06 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित। सुपर ऐलीवेशन, दीवार निर्माण एंव सोलिंग का कार्य पूर्ण। इण्टर कोट का कार्य प्रगति पर। -- as on 01-Jul-2024