Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 2.000 | 0.000 |
70W499 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 38666, दि0 10.01.2024
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 116.93 Lacs
Resanction Cost : 116.93 Lacs
Exp. Upto Last Fy : 0.22 Lacs
For CFY 2024-2025
Remaining : 116.71 Lacs
Demand : 80.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.22 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 5 %
Up to Date : 5 %
Sanction on :
4 months 1 week ago
10 Jan 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित। सुपर ऐलीवेशन एंव दीवार निर्माण का कार्य प्रगति पर। -- as on 28-Mar-2024
Physical Peramenters