Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.75 | 1.75 | 0.000 | 1.75 | 1.750 | 0.000 |
70W502 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 50713, दि0 25.01.2024।
TS Amount (lakhs) : 65.29 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
65.29
Resanction Cost :
65.29
Tentative Cost :
65.29
Exp. Upto Last Fy : 0.24
For CFY 2024-2025
Remaining : 65.05
Demand : 30.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.24
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 10 %
Sanction on :
5 months 3 weeks ago
25 Jan 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठित। कार्य प्रारम्भ किया जा रहा है। -- as on 28-Mar-2024
Physical Peramenters