Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 0.500 | 3.5 | 0.000 | 0.000 |
70W503 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 50713, दि0 25.01.2024।
TS Amount (lakhs) : 100.41 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
100.41
Resanction Cost :
100.41
Tentative Cost :
100.41
Exp. Upto Last Fy : 0.52
For CFY 2024-2025
Remaining : 99.89
Demand : 37.66
Allotment : 0.00
Exp in CFY : 18.57
Total Up to Date Exp : 19.09
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 45 %
Sanction on :
5 months 3 weeks ago
25 Jan 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य प्रगति पर। -- as on 28-Mar-2024
Physical Peramenters