Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 2.5 | 0.000 | 2.5 | 2.500 | 0.000 |
70W504 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 50713, दि0 25.01.2024।
TS Amount (lakhs) : 78.14 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
78.14
Resanction Cost :
78.14
Tentative Cost :
78.14
Exp. Upto Last Fy : 0.43
For CFY 2024-2025
Remaining : 77.71
Demand : 45.60
Allotment : 0.00
Exp in CFY : 15.60
Total Up to Date Exp : 16.03
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 40 %
Sanction on :
5 months 3 weeks ago
25 Jan 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान का कार्य प्रगति पर। -- as on 28-Mar-2024