Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Span of Bridges [m] | 36 | 36 | 0.000 | 36 | 0.000 | 0.000 |
70W507 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 48114, दि0 25.01.2024
TS Amount (lakhs) : 6.55 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
6.55
Resanction Cost :
6.55
Tentative Cost :
6.55
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 6.55
Demand : 2.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
5 months 3 weeks ago
25 Jan 2024
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
निविदा प्राप्त। अनुबन्ध गठन की कार्यवाही प्रगति पर। -- as on 07-Mar-2024
Physical Peramenters