Work Profile Report [70W510]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 48456, दि0 30.01.2024
TS Amount (lakhs) : 77.76 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
77.76
Resanction Cost :
77.76
Tentative Cost :
77.76
Exp. Upto Last Fy :
0.25
For CFY 2024-2025
Remaining :
77.51
Demand :
77.51
Allotment :
65.00
Exp in CFY :
64.92
Total Up to Date Exp :
65.17
Work completed
Sanction on : 9 months 3 weeks ago
30 Jan 2024
Physical Progress:
At start of FY 2024-2025 :
5 %
Up to Date :
100 %
Tentative Completion date on : 3 months 2 weeks ago
06 Aug 2024
Actual Completion Date : 5 months 16 hours ago
23 Jun 2024
Physical Linear Components
Remark
कार्य पूर्ण। दायित्वों का अन्तिमीकरण किया जा रहा है। -- as on 25-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand