Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6.7 | 6.7 | 0.000 | 6.7 | 4.000 | 0.000 |
70W511 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन की ई0 पत्रावली सं0 48456, दि0 30.01.2024
TS Amount (lakhs) : 185.6 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
185.60
Resanction Cost :
185.60
Tentative Cost :
185.60
Exp. Upto Last Fy : 0.27
For CFY 2024-2025
Remaining : 185.33
Demand : 185.33
Allotment : 20.00
Exp in CFY : 0.40
Total Up to Date Exp : 0.66
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 10 %
Sanction on :
5 months 2 weeks ago
30 Jan 2024
Tentative Completion date:
4 months 4 weeks from now
15 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
दीवार निर्माण का कार्य प्रगति पर। -- as on 15-Jun-2024