Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 27.5 | 27.5 | 0.000 | 27.5 | 0.000 | 0.000 |
70W512 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन के पत्रांक 212/।।।(2)/2024-01(प्रा0आ0)/2023, दि0 31.01.2024
TS Amount (lakhs) : 466.1 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
466.10
Resanction Cost :
466.10
Tentative Cost :
466.10
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 466.10
Demand : 466.10
Allotment : 150.00
Exp in CFY : 200.60
Total Up to Date Exp : 200.60
Construction Started
Physical Progress:
At start of FY 2024-2025 : 1 %
Up to Date : 80 %
Sanction on :
5 months 2 weeks ago
31 Jan 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
क्रैश बैरियर लगाये जाने का कार्य प्रगति पर। -- as on 02-Jul-2024
Physical Peramenters