Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 1.500 | 0.5 | 0.500 | 0.000 |
70W52 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 2712/।।।(2)/17-36(एम0एल0ए0)/ 2017 दि0 17.10.2017
TS Amount (lakhs) : 110.54 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
110.54
Resanction Cost :
110.54
Tentative Cost :
110.54
Exp. Upto Last Fy : 94.98
For CFY 2024-2025
Remaining : 15.56
Demand : 10.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 94.98
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
6 years 9 months ago
17 Oct 2017
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
1. तकनीकी स्वीकृति माह 05/2018 में प्राप्त।
2. स्वीकृत संरेखण पर ग्रामीणों द्वारा विवाद।
3. पहाड़ कटान का कार्य पूर्ण।
4. पार्ट-2 का कार्य प्रगति पर।
-- as on 15-Nov-2023
Physical Peramenters