Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 32 | 32 | 32 | 0 |
70W533 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन के पत्रांक सं0 294/।।।(3)/2024-01(सी0आर0आई0एफ0)2024, दि0 12.03.2024 एवं पत्रांक 256/।।।(3)/2024-01(सी0आर0आई0एफ0)2022, दि0 09.02.2024, एवं 322/।।।(3)/2024-14(सी0आर0आई0एफ0)2024, दि0 06-03-2024
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 1,593.52 Lacs
Resanction Cost : 1,593.52 Lacs
Exp. Upto Last Fy : 160.00 Lacs
For CFY 2024-2025
Remaining : 1,433.52 Lacs
Demand : 1,433.52 Lacs
Allotment : 717.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 160.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
2 months 1 week ago
12 Mar 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 10-Apr-2024
Physical Peramenters