Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 32 | 32 | 32 | 0 |
70W533 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शासन के पत्रांक सं0 294/।।।(3)/2024-01(सी0आर0आई0एफ0)2024, दि0 12.03.2024 एवं पत्रांक 256/।।।(3)/2024-01(सी0आर0आई0एफ0)2022, दि0 09.02.2024, एवं 322/।।।(3)/2024-14(सी0आर0आई0एफ0)2024, दि0 06-03-2024
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1593.52
Resanction Cost :
1593.52
Tentative Cost :
1593.52
Exp. Upto Last Fy : 160.00
For CFY 2024-2025
Remaining : 1,433.52
Demand : 1,433.52
Allotment : 717.00
Exp in CFY : 700.00
Total Up to Date Exp : 860.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 50 %
Sanction on :
4 months 5 days ago
12 Mar 2024
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
उक्त कार्य ब्रिडकुल कार्यदायी संस्था द्वारा कराया जा रहा है। -- as on 02-Jun-2024
Physical Peramenters