Work Profile Report [70W57]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : शा0सं0 1371/।।।(2)21-40(एम0एल0ए0) 2017 टी0सी0 ।।। दिनांक 21.05.2021
TS Amount (lakhs) : 107 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
23.35
Resanction Cost :
23.35
Tentative Cost :
23.35
Exp. Upto Last Fy :
8.72
For CFY 2024-2025
Remaining :
14.63
Demand :
4.63
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
8.72
Construction Started
Sanction on : 3 years 6 months ago
21 May 2021
Physical Progress:
At start of FY 2024-2025 :
35 %
Up to Date :
50 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
मुआवजा गठित। वितरण प्रक्रिया गतिमान। -- as on 02-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand