Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 0.000 | 2.5 | 0.000 | 0.000 |
70W57 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1371/।।।(2)21-40(एम0एल0ए0) 2017 टी0सी0 ।।। दिनांक 21.05.2021
TS Amount (lakhs) : 107 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
23.35
Resanction Cost :
23.35
Tentative Cost :
23.35
Exp. Upto Last Fy : 8.72
For CFY 2024-2025
Remaining : 14.63
Demand : 4.63
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 8.72
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 35 %
Sanction on :
3 years 1 month ago
21 May 2021
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
प्रथम चरण का कार्य लगभग पूर्ण। मुआवजा गठन की कार्यवाही की जा रही है। -- as on 14-Jul-2022
Physical Peramenters