Work Profile Report [70W65]

जयहरीखाल के अन्तर्गत ग्राम मैन्दोली-परिन्दा- बौठा- डेरियाखाल मो0 मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Forest
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0774 /111/-(2) /06-103 (प्रा0आ0)/05 दि0 26.3.06

TS Amount (lakhs) : 343.86 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

172.50

Resanction Cost :

172.50

Tentative Cost :

172.50

Exp. Upto Last Fy :

75.67

For CFY 2025-2026

Remaining :

96.83

Demand :

96.83

Allotment :

40.00

Exp in CFY :

33.25

Total Up to Date Exp :

108.92

Construction Started

Sanction on : 19 years 4 months ago

26 Mar 2006

Physical Progress:

At start of FY 2025-2026 :

60 %

Up to Date :

80 %

Tentative Completion date on : 7 months 3 weeks from now

31 Mar 2026

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
10
10
4.000
6
4.000
0.000

Remark

view all

पहाड़ कटान का कार्य प्रगति पर।
दिनांक 02व 05.08.2025 के परिवेश पोर्टल के स्टेटस के अनुसार यह प्रस्ताव नोडल अधिकारी स्तर पर लम्बित है।
-- as on 06-Aug-2025

Rating : 87

Forest Case Pending At : 15: AIP Nodal

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: