Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 10 | 0.000 | 10 | 5.000 | 0.000 |
70W65 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0774 /111/-(2) /06-103 (प्रा0आ0)/05 दि0 26.3.06
TS Amount (lakhs) : 171.36 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
172.50
Resanction Cost :
172.50
Tentative Cost :
172.50
Exp. Upto Last Fy : 32.73
For CFY 2024-2025
Remaining : 139.77
Demand : 30.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 32.73
in Tendering Stage
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 10 %
Sanction on :
18 years 3 months ago
26 Mar 2006
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Forest Status 13: AIP DFO
Bottelneck: no issue
उपरोक्त मोटर मार्ग की सैद्धान्तिक स्वीकृति प्राप्त होने के उपरान्त विधिवत स्वीकृति हेतु हेतु अनुपालन आख्या इस कार्यालय के पत्रांक सं0 477/21सी0, दि0 26-02-2022 द्वारा प्रभागीय वनाधिकारी गढ़वाल वन प्रभाग पौड़ी को प्रेषित। वर्तमान में मार्ग में आ रहे वृक्षों के छपान कार्य पूर्ण कर लिया गया है। निर्माण कार्य हेतु निविदा आमन्त्रित की गयी जिसमें प्रथम बार में कोई निविदा प्राप्त नहीं हुयी। दूसरी बार निविदा आमन्त्रित करने पर निविदा उच्च दरों पर प्राप्त हुयी है। पुनः निविदा आमन्तित्र की गयी है। उपरोक्त मोटर मार्ग की सैद्धान्तिक स्वीकृति प्राप्त होने के उपरान्त विधिवत स्वीकृति हेतु हेतु अनुपालन आख्या इस कार्यालय के पत्रांक सं0 477/21सी0, दि0 26-02-2022 द्वारा प्रभागीय वनाधिकारी गढ़वाल वन प्रभाग पौड़ी को प्रेषित।भुगतान की गयी धनराशि आॅनलाइन प्रदर्शित न होने के कारण दि0 22.05.2024 को पोर्टल पर शिकायत सं0 पी0ए0आर0टी0आई0सी0-24009279 एंव 24009297, दि0 22.05.2024 के द्वारा आॅनलाइ्रन शिकायत दर्ज करायी गयी है। -- as on 27-May-2024
Physical Peramenters