Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.8 | 0.8 | 0.000 | 0.8 | 0.500 | 0.000 |
70W69 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : fजलाfधकारी पौड़ी का पत्रांक 589/वा0fज0यो0/ 2017-18 fद0 30.08.2017
TS Amount (lakhs) : 28.56 Lacs
Financial Detail
Sanction Cost : 28.56 Lacs
Resanction Cost : 28.56 Lacs
Exp. Upto Last Fy : 17.60 Lacs
For CFY 2024-2025
Remaining : 10.96 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 17.60 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 15 %
Up to Date : 15 %
Sanction on :
6 years 8 months ago
30 Aug 2017
Tentative Completion date:
2 years 1 month ago
31 Mar 2022
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सोलिंग बिछाने का कार्य प्रगति पर। -- as on 03-Jun-2023
Physical Peramenters