Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 0.000 | 6 | 0.000 | 0.000 |
70W71 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 4842(1)/111(2)/11-30(एम0एल0ए0) /2011 दि0 10.10.2011
TS Amount (lakhs) : 40.15 Lacs
Financial Detail
Sanction Cost : 75.48 Lacs
Resanction Cost : 75.48 Lacs
Exp. Upto Last Fy : 62.34 Lacs
For CFY 2024-2025
Remaining : 13.14 Lacs
Demand : 2.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 62.34 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 85 %
Sanction on :
12 years 7 months ago
10 Oct 2011
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
तकनीकी स्वीकृति प्राप्त प्रथम चरण के कार्य लगभग पूर्ण मुआवजा भुगतान किया गया है। अवशेष मुआवजे का भुगतान किया जा रहा है। -- as on 08-Dec-2022
Physical Peramenters