Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 6 | 6 | 0.000 | 6 | 0.000 | 0.000 |
70W71 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 4842(1)/111(2)/11-30(एम0एल0ए0) /2011 दि0 10.10.2011
TS Amount (lakhs) : 40.15 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
75.48
Resanction Cost :
75.48
Tentative Cost :
75.48
Exp. Upto Last Fy : 62.34
For CFY 2024-2025
Remaining : 13.14
Demand : 2.20
Allotment : 0.00
Exp in CFY : 2.20
Total Up to Date Exp : 64.55
Construction Started
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 85 %
Sanction on :
12 years 9 months ago
10 Oct 2011
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
तकनीकी स्वीकृति प्राप्त प्रथम चरण के कार्य लगभग पूर्ण मुआवजा भुगतान किया गया है। अवशेष मुआवजे का भुगतान किया जा रहा है। -- as on 08-Dec-2022
Physical Peramenters