Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 2.000 | 3 | 3.000 | 0.000 |
70W72 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 764/111(2)/08 दिनांक 24.03.2008
TS Amount (lakhs) : 175 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
175.00
Resanction Cost :
175.00
Tentative Cost :
175.00
Exp. Upto Last Fy : 44.79
For CFY 2024-2025
Remaining : 130.21
Demand : 57.28
Allotment : 0.00
Exp in CFY : 2.28
Total Up to Date Exp : 47.07
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 60 %
Sanction on :
16 years 3 months ago
24 Mar 2008
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
वास्तविक लम्बाई 3.00 किमी0 में पहाड़ कटान का कार्य पूर्ण। पार्ट-2 का कार्य प्रगति पर। -- as on 02-Jun-2024
Physical Peramenters