Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 2.000 | 1 | 0.000 | 0.000 |
70W82 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 1541/।।।(2)/09-23(मु0मं0घो0)/09 दि0 31.03.2010
TS Amount (lakhs) : 86.11 Lacs
Financial Detail
Sanction Cost : 105.00 Lacs
Resanction Cost : 105.00 Lacs
Exp. Upto Last Fy : 63.57 Lacs
For CFY 2024-2025
Remaining : 41.43 Lacs
Demand : 20.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 63.57 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
14 years 1 month ago
31 Mar 2010
Tentative Completion date:
5 months 2 weeks ago
29 Nov 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
स्वीकृत लम्बाई 3.00 किमी0 के सापेक्ष वास्तविक लम्बाई 2.00 किमी0 में मार्ग निर्माण का कार्य पूर्ण। -- as on 28-Mar-2024
Physical Peramenters