Work Profile Report [70W82]

धुमाकोट विधानसभा क्षेत्र के अन्तर्गत मैन्दोली-कोटा मोटर मार्ग।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

  • Aggrements
  • Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 1541/।।।(2)/09-23(मु0मं0घो0)/09 दि0 31.03.2010

TS Amount (lakhs) : 86.11 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

105.00

Resanction Cost :

105.00

Tentative Cost :

105.00

Exp. Upto Last Fy :

71.30

For CFY 2025-2026

Remaining :

33.70

Demand :

0.00

Allotment :

0.00

Exp in CFY :

0.00

Total Up to Date Exp :

71.30

Work completed

Sanction on : 15 years 3 months ago

31 Mar 2010

Physical Progress:

At start of FY 2025-2026 :

100 %

Up to Date :

100 %

Tentative Completion date on : 2 months 6 days ago

30 Apr 2025

Actual Completion Date : 1 year 8 months ago

31 Oct 2023

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3
3
3
-

Remark

view all

2 किमी0 में पहाड़ कटान पूर्ण। मुआवजा वितरण की कार्यवाही गतिमान। -- as on 09-Apr-2025

Rating : 100

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand