Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.000 | 0.000 |
70W86 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0 5150/111(2)/10-18(प्रा0आ0)/2010 दि0 16.8.10
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
63.00
Resanction Cost :
63.00
Tentative Cost :
63.00
Exp. Upto Last Fy : 60.23
For CFY 2024-2025
Remaining : 2.77
Demand : 2.78
Allotment : 0.00
Exp in CFY : 0.99
Total Up to Date Exp : 61.22
Construction Started
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 85 %
Sanction on :
13 years 11 months ago
16 Aug 2010
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
80 प्रतिशत में मुआवजा वितरित किया जा चुका है। काश्तकारों के न आने के कारण मुआवजा भुगतान अवशेष। -- as on 28-Mar-2024
Physical Peramenters