Work Profile Report [70W86]

जनपद पौड़ी गढ़वाल के विधानसभा क्षेत्र यमकेश्वर के अन्तर्गत सिलोगी-धनसाली मोटर मार्ग का विस्तार।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 5150/111(2)/10-18(प्रा0आ0)/2010 दि0 16.8.10

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

63.00

Resanction Cost :

63.00

Tentative Cost :

63.00

Exp. Upto Last Fy :

60.23

For CFY 2024-2025

Remaining :

2.77

Demand :

2.78

Allotment :

2.50

Exp in CFY :

0.99

Total Up to Date Exp :

61.22

Construction Started

Sanction on : 14 years 3 months ago

16 Aug 2010

Physical Progress:

At start of FY 2024-2025 :

85 %

Up to Date :

85 %

Tentative Completion date on : 7 months 3 weeks ago

31 Mar 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2024-2025
Remaining
Target
Achievement
Road [Km]
5
5
0.000
5
0.000
0.000

Remark

view all

80 प्रतिशत में मुआवजा वितरित किया जा चुका है। काश्तकारों के न आने के कारण मुआवजा भुगतान अवशेष। -- as on 28-Mar-2024

Rating : 97

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI:

© PWD Uttarakhand