Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 12 | 12 | 0.000 | 12 | 10.000 | 0.000 |
71W1015 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : ई पत्रावली संख्या 64127 दिनांक 13/03/2024
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 1,825.35 Lacs
Resanction Cost : 1,825.35 Lacs
Exp. Upto Last Fy : 0.16 Lacs
For CFY 2024-2025
Remaining : 1,825.19 Lacs
Demand : 800.00 Lacs
Allotment : 50.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.16 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 10 %
Sanction on :
2 months 6 days ago
13 Mar 2024
Tentative Completion date:
8 months 1 week from now
30 Jan 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 06-Apr-2024
Physical Peramenters