Work Profile

fदयोड़-धामधार मोटर मार्ग का fनर्माण।


Work not linked with IM

Bridges on The Basis of AI:

Administrative Approval Detail : शा0सं0-2884/।।।-(2)/06-56(प्रा0आ0)/06 दि0 10/11/2006

TS Amount (lakhs) : 172.5 Lacs

Financial Detail

Sanction Cost : 172.50 Lacs

Resanction Cost : 172.50 Lacs

Exp. Upto Last Fy : 120.53 Lacs

For CFY 2024-2025

Remaining : 51.97 Lacs

Demand : 50.00 Lacs

Allotment : 20.00 Lacs

Exp in CFY : 0.00 Lacs

Total Up to Date Exp : 120.53 Lacs

Construction Started

Physical Progress:

At start of FY 2024-2025 : 75 %

Up to Date : 75 %

Sanction on :
17 years 6 months ago
10 Nov 2006


Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024


Actual Completion Date:
Not Yet Reported


Rating : 75

Remark

Bottelneck: no issue


पहाड़ कटान कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 01-May-2024

Physical Peramenters

Particulars Sanction Resanction Upto Last Fy For Cfy 2024-2025
Remaining Target Achievement
Length of Road [Km] 10 8.5 5.000 3.5 0.600 0.600