Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 10 | 8.5 | 5.000 | 3.5 | 0.600 | 0.600 |
71W184 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-2884/।।।-(2)/06-56(प्रा0आ0)/06 दि0 10/11/2006
TS Amount (lakhs) : 172.5 Lacs
Financial Detail
Sanction Cost : 172.50 Lacs
Resanction Cost : 172.50 Lacs
Exp. Upto Last Fy : 120.53 Lacs
For CFY 2024-2025
Remaining : 51.97 Lacs
Demand : 50.00 Lacs
Allotment : 20.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 120.53 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 75 %
Up to Date : 75 %
Sanction on :
17 years 6 months ago
10 Nov 2006
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान कार्य पूर्ण। शेष कार्य प्रगति पर। -- as on 01-May-2024