Work Profile Report [71W385]

मा0मुख्यमंत्री जी की घोषणा सं0-462/2015 के अन्तर्गत स्यालनी मोटर मार्ग का निर्माण।
  • Work Detail
  • General Detail
  • Expenditure
  • Fin Plan
  • Components
  • Remarks
  • Tenders

    Aggrements

    Project Activities

    alerts

    Documents

    Samples

Administrative Approval Detail : शा0सं0 2724/।।।(2)/ 15-05(मु0मं0घो0)/2015 दिनांक 23.04.2015

TS Amount (lakhs) : 0 Lacs

Budget Financial Head : State Sector ⮚

Financial Detail

(All Amount in Rs Lakhs)

Sanction Cost :

41.31

Resanction Cost :

41.31

Tentative Cost :

41.31

Exp. Upto Last Fy :

2.93

For CFY 2025-2026

Remaining :

38.38

Demand :

6.00

Allotment :

6.00

Exp in CFY :

5.14

Total Up to Date Exp :

8.07

Construction Started

Sanction on : 10 years 3 months ago

23 Apr 2015

Physical Progress:

At start of FY 2025-2026 :

1 %

Up to Date :

15 %

Tentative Completion date on : 1 year 4 months ago

31 Mar 2024

Actual Completion Date :

Not Yet Reported

Physical Linear Components

Particulars
Sanction
Resanction
Upto Last Fy
For cfy 2025-2026
Remaining
Target
Achievement
Road [Km]
3
3
0.000
3
0.000
0.000

Remark

view all

fद्वतीय चरण की स्वीकृfत प्राप्त। -- as on 14-Jun-2021

Rating : 7

No Forest Case in The Work

No Hindrance / Bottleneck

Assets :

Work not linked with IM

Bridges on The Basis of AI: