Work Profile Report [71W385]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0 2724/।।।(2)/ 15-05(मु0मं0घो0)/2015 दिनांक 23.04.2015
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
41.31
Resanction Cost :
41.31
Tentative Cost :
41.31
Exp. Upto Last Fy :
2.93
For CFY 2025-2026
Remaining :
38.38
Demand :
6.00
Allotment :
6.00
Exp in CFY :
5.14
Total Up to Date Exp :
8.07
Construction Started
Sanction on : 10 years 3 months ago
23 Apr 2015
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
15 %
Tentative Completion date on : 1 year 4 months ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
fद्वतीय चरण की स्वीकृfत प्राप्त। -- as on 14-Jun-2021
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand