Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 5 | 0 |
71W409 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 4520/।।।(2)/ 15-08(मु0मं0घो0)/2015 दिनांक 19.06.2015
TS Amount (lakhs) : 1.05 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1.05
Resanction Cost :
1.05
Tentative Cost :
1.05
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 0.95
Demand : 0.95
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 9 %
Up to Date : 9 %
Sanction on :
9 years 4 weeks ago
19 Jun 2015
Tentative Completion date:
6 months 3 weeks ago
25 Dec 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पुनः विस्तृत आगणन गठित कर मुख्य अभियन्ता, पौड़ी के पत्रांक-4592/ 12 (34) याता-दुगड्डा पौड़ी/ 2023 दि0 9/8/2023 द्वारा रू0 276.18 लाख मात्र का सचिव, लो0नि0वि0, उत्तराखण्ड शासन को स्वीकृति हेतु प्रेषित। -- as on 02-Jan-2024
Physical Peramenters