Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.5 | 0.5 | 0.5 | 0 |
71W450 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : fजलाfधकारी, पौड़ी के पत्रांक -487/fज0यो0/लो0fन0fव0/ 2015-16 fद 08/07/15
TS Amount (lakhs) : 25.9 Lacs
Financial Detail
Sanction Cost : 25.90 Lacs
Resanction Cost : 25.90 Lacs
Exp. Upto Last Fy : 3.61 Lacs
For CFY 2024-2025
Remaining : 22.29 Lacs
Demand : 10.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 3.61 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 20 %
Sanction on :
8 years 10 months ago
08 Jul 2015
Tentative Completion date:
4 months 2 weeks ago
31 Dec 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 31-Dec-2020
Physical Peramenters