Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Buildings | 1 | 1 | 1 | 0 | 0 | 0 |
71W461 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : fनयोजन/1237-40/24-fनर्माण/2015-16 fदनांक 20/7/2015
TS Amount (lakhs) : 59.25 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
42.61
Resanction Cost :
59.25
Tentative Cost :
59.25
Exp. Upto Last Fy : 36.66
For CFY 2024-2025
Remaining : 22.59
Demand : 22.59
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 36.66
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
8 years 11 months ago
20 Jul 2015
Tentative Completion date:
2 years 10 months ago
31 Aug 2021
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। दिनांक 27.10.16 को प्रधानाचार्य द्वारा भवन अधिग्रहण कर लिया गया है। पुनःरीक्षित स्वीकृति के अन्तर्गत भवन कार्य पूर्ण। दायित्व शेष। fद0 9/6/19 द्वारा भवन प्रधानाचार्य को हस्तान्तfरत कर fदया गया है तथा उपयोfगता प्रमाण इस कार्यालय के पत्रांक-2164/5सी0 fद0 4/7/19 द्वारा fजला पfरयोजना अfधकारी रमसा पौड़ी को प्रेfषत। धनावंटन हेतु पत्र fलखा गया है। -- as on 31-Jan-2021
Physical Peramenters