Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.5 | 0.5 | 0.000 | 0.5 | 0.500 | 0.000 |
71W538 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : fजलाfधकारी, पौड़ी के पत्रांक -04/fज0यो0/2017-18 fद 01/12/17
TS Amount (lakhs) : 17.5 Lacs
Financial Detail
Sanction Cost : 17.50 Lacs
Resanction Cost : 17.50 Lacs
Exp. Upto Last Fy : 4.95 Lacs
For CFY 2024-2025
Remaining : 12.55 Lacs
Demand : 5.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 4.95 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 40 %
Up to Date : 40 %
Sanction on :
6 years 5 months ago
01 Dec 2017
Tentative Completion date:
3 months 2 weeks ago
31 Jan 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान पूर्ण। भाग दो कार्य की निविदा आमंत्रित की जा चुकी है। -- as on 06-Oct-2022
Physical Peramenters