Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.5 | 2.5 | 2.000 | 0.5 | 0.500 | 0.500 |
71W583 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-1075/।।।(2)/19-36(एम0एल0ए0)/2017 टी0सी0 ।। दि0 27/2/2019
TS Amount (lakhs) : 139.83 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
139.91
Resanction Cost :
139.91
Tentative Cost :
139.91
Exp. Upto Last Fy : 64.55
For CFY 2024-2025
Remaining : 75.36
Demand : 74.35
Allotment : 4.55
Exp in CFY : 4.55
Total Up to Date Exp : 69.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 28 %
Up to Date : 50 %
Sanction on :
5 years 4 months ago
27 Feb 2019
Tentative Completion date:
8 months 1 week from now
25 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
पहाड़ कटान कार्य पूर्ण । शेष कार्य प्रगति पर। -- as on 01-May-2024
Physical Peramenters