Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3 | 0 | ||
No of Bridges | 1 | 1 | 1 | 0 | ||
Span of Bridges [m] | 30 | 30 | 30 | 0 |
71W599 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शा0सं0-697/।।।(2)/19-40(एम0एल0ए0)/2017 दि0 18/2/2019
TS Amount (lakhs) : 41.4 Lacs
Financial Detail
Sanction Cost : 41.40 Lacs
Resanction Cost : 41.40 Lacs
Exp. Upto Last Fy : 6.55 Lacs
For CFY 2024-2025
Remaining : 34.85 Lacs
Demand : 15.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 6.55 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 12 %
Up to Date : 12 %
Sanction on :
5 years 3 months ago
18 Feb 2019
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
द्वितीय चरण की स्वीकृति प्राप्त। सेतु कार्य की डी0पी0आर0 अधीक्षण अभियन्ता पौड़ी के पत्रांक-1911/100 याता-12/2023 दि0 16/3/24 द्वारा रू0 365.73 लाख मात्र की मुख्य अभियन्ता, पौड़ी को प्रेषित। -- as on 05-Apr-2024
Physical Peramenters