Work Profile Report [71W680]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : श्शा0सं0-1418/।।।(2)/21-40(एम0एल0ए0)/2017 टी0सी0-1 दिनांक 31/5/2021
TS Amount (lakhs) : 7.44 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
30.45
Resanction Cost :
30.45
Tentative Cost :
30.45
Exp. Upto Last Fy :
1.34
For CFY 2025-2026
Remaining :
29.11
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
1.34
Construction Started
Sanction on : 4 years 7 months ago
31 May 2021
Physical Progress:
At start of FY 2025-2026 :
4 %
Up to Date :
4 %
Tentative Completion date on : 2 years 9 months from now
31 Oct 2028
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
द्वितीय चरण की स्वीकृति प्राप्त। -- as on 14-Jan-2022
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© 2026 PWD Uttarakhand