Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 2.800 | 0.2 | 0.200 | 0.200 |
71W683 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0.1422ध्।।।;2द्धध्21.36;एम0एल0ए0द्धध्2017 टी0सी0 दिनांक 1ध्6ध्2021
TS Amount (lakhs) : 129.62 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
64.81
Resanction Cost :
64.81
Tentative Cost :
64.81
Exp. Upto Last Fy : 58.78
For CFY 2024-2025
Remaining : 6.03
Demand : 6.00
Allotment : 4.10
Exp in CFY : 4.10
Total Up to Date Exp : 62.88
Work completed
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 100 %
Sanction on :
3 years 1 month ago
01 Jun 2021
Tentative Completion date:
2 months 2 weeks ago
30 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 01-May-2024
Physical Peramenters