Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.525 | 4.525 | 3.000 | 1.525 | 1.520 | 0.000 |
71W685 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0.1426ध्।।।;2द्धध्21.36;एम0एल0ए0द्धध्2017 टी0सी0.3 दिनांक 1ध्6ध्2021
TS Amount (lakhs) : 72.91 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
72.91
Resanction Cost :
72.91
Tentative Cost :
72.91
Exp. Upto Last Fy : 38.96
For CFY 2024-2025
Remaining : 33.95
Demand : 30.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 38.96
Construction Started
Physical Progress:
At start of FY 2024-2025 : 30 %
Up to Date : 30 %
Sanction on :
3 years 1 month ago
01 Jun 2021
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 09-Nov-2021
Physical Peramenters