Work Profile Report [71W685]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0सं0.1426ध्।।।;2द्धध्21.36;एम0एल0ए0द्धध्2017 टी0सी0.3 दिनांक 1ध्6ध्2021
TS Amount (lakhs) : 72.91 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
72.91
Resanction Cost :
72.91
Tentative Cost :
72.91
Exp. Upto Last Fy :
38.96
For CFY 2024-2025
Remaining :
33.95
Demand :
5.00
Allotment :
6.09
Exp in CFY :
6.09
Total Up to Date Exp :
45.05
Construction Started
Sanction on : 3 years 6 months ago
01 Jun 2021
Physical Progress:
At start of FY 2024-2025 :
30 %
Up to Date :
30 %
Tentative Completion date on : 8 months 3 weeks ago
31 Mar 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
3.50 कि0मी0 में पहाड़ कटान कार्य पूर्ण। इससे आगे ग्रामवासियों द्वारा विवाद किया जा रहा है। -- as on 03-Sep-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: