Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 1.300 | 0.2 | 0.000 | 0.000 |
71W686 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0.1426ध्।।।;2द्धध्21.36;एम0एल0ए0द्धध्2017 टी0सी0.3 दिनांक 1ध्6ध्2021
TS Amount (lakhs) : 28.53 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
28.53
Resanction Cost :
28.53
Tentative Cost :
28.53
Exp. Upto Last Fy : 21.05
For CFY 2024-2025
Remaining : 7.48
Demand : 7.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 21.05
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 1 month ago
01 Jun 2021
Tentative Completion date:
1 year 2 weeks ago
30 Jun 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्णं। -- as on 07-Nov-2023
Physical Peramenters