Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2.000 | 0 | 0.000 | 0.000 |
71W687 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0.1426ध्।।।;2द्धध्21.36;एम0एल0ए0द्धध्2017 टी0सी0.3 दिनांक 1ध्6ध्2021
TS Amount (lakhs) : 116.02 Lacs
Financial Detail
Sanction Cost : 58.01 Lacs
Resanction Cost : 58.01 Lacs
Exp. Upto Last Fy : 15.49 Lacs
For CFY 2024-2025
Remaining : 42.52 Lacs
Demand : 40.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 15.49 Lacs
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
01 Jun 2021
Tentative Completion date:
5 months 2 weeks ago
30 Nov 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 02-Dec-2023