Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 3.000 | 0 | 0.000 | 0.000 |
71W709 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 2393(1)/।।। (2 )/ 21-40 (एम0एल0ए0) /2017 टी0सी0 दिनांक 4/8/2021
TS Amount (lakhs) : 72.85 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
72.85
Resanction Cost :
72.85
Tentative Cost :
72.85
Exp. Upto Last Fy : 50.06
For CFY 2024-2025
Remaining : 22.79
Demand : 22.00
Allotment : 9.97
Exp in CFY : 9.97
Total Up to Date Exp : 60.03
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
04 Aug 2021
Tentative Completion date:
1 year 2 months ago
30 Apr 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 05-Apr-2024