Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.586 | 2.586 | 1.000 | 1.586 | 0.000 | 0.000 |
71W713 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 3256/।।।(2)/ 21- 41 (एम0एल0ए0) /2017 टी0सी0 ।। दि0 2/9/2021
TS Amount (lakhs) : 120.4 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
120.40
Resanction Cost :
120.40
Tentative Cost :
120.40
Exp. Upto Last Fy : 43.22
For CFY 2024-2025
Remaining : 77.18
Demand : 20.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 43.22
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
02 Sep 2021
Tentative Completion date:
1 year 2 months ago
30 Apr 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। शेष मार्ग नगर निगम द्वारा बना दिया गया है। -- as on 01-May-2024
Physical Peramenters