Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.465 | 3.465 | 2.900 | 0.565 | 0.000 | 0.000 |
71W717 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0-3260/।।। (2)/ 21- 41 (एम0एल0ए0) /2017 दिनांक 2/9/2021
TS Amount (lakhs) : 163.19 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
163.19
Resanction Cost :
163.19
Tentative Cost :
163.19
Exp. Upto Last Fy : 135.26
For CFY 2024-2025
Remaining : 27.93
Demand : 25.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 135.26
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 10 months ago
02 Sep 2021
Tentative Completion date:
1 year 2 months ago
30 Apr 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। अवशेष देयकों के भुगतान की कार्यवाही की जा रही है। शेष मार्ग नगर निगम द्वारा बना दिया गया है। -- as on 07-Nov-2023