Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.775 | 0.775 | 0.600 | 0.175 | 0.000 | 0.000 |
71W730 :
Work not linked with IM
Bridges on The Basis of AI: GODI BADI
Administrative Approval Detail : शा0-4935/।।। (2)/ 21- 41 (एम0एल0ए0) /2017टी0सी0आई0 दिनांक 13/10/2021
TS Amount (lakhs) : 26.87 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
26.87
Resanction Cost :
26.87
Tentative Cost :
26.87
Exp. Upto Last Fy : 18.00
For CFY 2024-2025
Remaining : 8.87
Demand : 8.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 18.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 85 %
Up to Date : 85 %
Sanction on :
2 years 9 months ago
13 Oct 2021
Tentative Completion date:
11 months 2 weeks ago
31 Jul 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
0.60 कि0मी0 लम्बाई में कार्य पूर्ण। शेष कार्य नगर निगम द्वारा किया जा चुका है। -- as on 02-Dec-2023
Physical Peramenters