Administrative Approval Detail : शा0-1172/।।। (3)/2021-14 (सी0आर0आई0एफ0) /2021 दि0 27/10/2021
TS Amount (lakhs) : 2019.57 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
2019.57
Resanction Cost :
2019.57
Tentative Cost :
2019.57
Exp. Upto Last Fy :
2,019.38
For CFY 2024-2025
Remaining :
0.19
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2,019.38
Work completed
Sanction on : 3 years 1 month ago
27 Oct 2021
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 8 months 3 weeks ago
31 Mar 2024
Actual Completion Date : 1 year 10 months ago
24 Feb 2023
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 06-Apr-2024
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: T BEAM T BEAM Podali Bridge HALDGADI BRIDGE RCC MINOR BRIDGE