Work Profile Report [71W732]
Fin Plan
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : शा0-1112/।।। (3)/2021-15 (सी0आर0आई0एफ0)/2021 दिनांक 4/10/2021
TS Amount (lakhs) : 114.55 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
114.55
Resanction Cost :
114.55
Tentative Cost :
114.55
Exp. Upto Last Fy :
45.74
For CFY 2024-2025
Remaining :
68.81
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
45.74
Construction Started
Sanction on : 3 years 2 months ago
04 Oct 2021
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
0 %
Tentative Completion date on : 2 years 8 months ago
31 Mar 2022
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
क्रेश बैरियर, डेलिनेटर एवं साईन बोर्ड का कार्य प्रगति पर है। -- as on 19-Feb-2022
Assets :
Work not linked with IM
Roads on The Basis of AI: Road 1
Bridges on The Basis of AI: GODI BADI ARCH BRIDGE 30 m Dugadda Juwa bridge