Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.64 | 3.64 | 2.300 | 1.34 | 0.000 | 0.000 |
71W733 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5379/।।। (2)/ 21-41 (एम0एल0ए0)/ 2017टी0सी0आई0 दिनांक 11/11/2021
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 106.21 Lacs
Resanction Cost : 106.21 Lacs
Exp. Upto Last Fy : 43.89 Lacs
For CFY 2024-2025
Remaining : 62.32 Lacs
Demand : 60.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 43.89 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
2 years 6 months ago
11 Nov 2021
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
2.30 कि0मी0 में पी0सी0 कार्य पूर्णं। शेष कार्य प्रगति पर। -- as on 01-Jul-2023
Physical Peramenters