Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.8 | 2.8 | 0.000 | 2.8 | 1.000 | 0.000 |
71W737 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0-5709/।।। (2)/ 21-40 (एम0एल0ए0)/ 2017टी0सी0।। दिनांक 25/11/2021
TS Amount (lakhs) : 147.88 Lacs
Financial Detail
Sanction Cost : 73.94 Lacs
Resanction Cost : 73.94 Lacs
Exp. Upto Last Fy : 0.00 Lacs
For CFY 2024-2025
Remaining : 73.94 Lacs
Demand : 40.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.00 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
2 years 5 months ago
25 Nov 2021
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
अनुबन्ध गठन की कार्यवाही की जा रही है। -- as on 01-Feb-2024
Physical Peramenters