Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2.000 | 0 | 0.000 | 0.000 |
71W746 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 6128/।।। (2)/ 21-36 (एम0एल0ए0)/ 2017टी0सी0 दिनांक 21/12/2021
TS Amount (lakhs) : 59.49 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
59.49
Resanction Cost :
59.49
Tentative Cost :
59.49
Exp. Upto Last Fy : 40.54
For CFY 2024-2025
Remaining : 18.95
Demand : 15.00
Allotment : 7.66
Exp in CFY : 7.66
Total Up to Date Exp : 48.20
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 6 months ago
21 Dec 2021
Tentative Completion date:
7 months 2 weeks ago
30 Nov 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 02-Dec-2023