Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4 | 4 | 3.500 | 0.5 | 0.500 | 0.000 |
71W763 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 430(1)/।।।(2)/22-40 (एम0एल0ए0)/2017 टी0सी0-।।। दिनांक 6/1/2022
TS Amount (lakhs) : 126.85 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
126.85
Resanction Cost :
126.85
Tentative Cost :
126.85
Exp. Upto Last Fy : 83.93
For CFY 2024-2025
Remaining : 42.92
Demand : 33.05
Allotment : 5.98
Exp in CFY : 5.98
Total Up to Date Exp : 89.91
Construction Started
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 60 %
Sanction on :
2 years 6 months ago
06 Jan 2022
Tentative Completion date:
7 months 2 weeks ago
30 Nov 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 02-Feb-2022
Physical Peramenters