Work Profile Report [71W766]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : 1391/Nabard(RIDF 25)2020-2021 DT 22/12/2020
TS Amount (lakhs) : 39.25 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
39.25
Resanction Cost :
39.25
Tentative Cost :
39.25
Exp. Upto Last Fy :
24.78
For CFY 2024-2025
Remaining :
14.47
Demand :
14.47
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
24.78
Work completed
Sanction on : 3 years 11 months ago
22 Dec 2020
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 3 months ago
31 Jul 2023
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। दायित्व शेष। -- as on 03-Aug-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand