Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Buildings | 1 | 1 | 1 | 0 |
71W766 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 1391/Nabard(RIDF 25)2020-2021 DT 22/12/2020
TS Amount (lakhs) : 39.25 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
39.25
Resanction Cost :
39.25
Tentative Cost :
39.25
Exp. Upto Last Fy : 24.78
For CFY 2024-2025
Remaining : 14.47
Demand : 14.47
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 24.78
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 6 months ago
22 Dec 2020
Tentative Completion date:
11 months 2 weeks ago
31 Jul 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। दायित्व शेष। -- as on 03-Aug-2023
Physical Peramenters