Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 1.000 | 0.5 | 0.500 | 0.000 |
71W767 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-CW/R/37/2022-III-2 Public Work Department (computer No 27857)/1/53033/2022 Dt 27/07/2022
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 28.01 Lacs
Resanction Cost : 28.01 Lacs
Exp. Upto Last Fy : 11.78 Lacs
For CFY 2024-2025
Remaining : 16.23 Lacs
Demand : 16.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 11.78 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 35 %
Up to Date : 35 %
Sanction on :
1 year 9 months ago
27 Jul 2022
Tentative Completion date:
1 month 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 06-Dec-2022
Physical Peramenters